The floor-placers are coming tomorrow to pour the ground floor slab. We have spent the last 2 days preparing for it by laying polythene, bending 'starters' (vertical reinforcing steel, bent flat into the slab), laying mesh, wire-tying, boxing up, laying down, running round....

The inspector has been through and all is good for the pour. Pray it doesn't rain or snow.